|
Exam Title: Certified in Production and Inventory Management (CPIM)
Exam Code: CPIM
Edition:
This (tutorial) will help you to know the range of things you need to know…
Question No. 1
Question No. 2
A schedule (priority plan) that establishes to show the components required at each level of the assembly and based on lead time, calculates the time when these component will be needed called:
- Material Requirements Planning
- Master Production Schedule
- Inventory control Planning
- B & C
Answer Key: A
Question No. 3
Question No. 4
If a company makes wooden tables, the demand for the tables is called
Independent Demand
Dependent Demand
Both A & B
None of the above
Answer Key: A
Question No. 5
Independent demand is:
- Directly related to the demand for any other products or assemblies
- Not related to the demand for any other products or assemblies
- Calculated
- A & C
Answer Key: B
Question No. 6
Question No. 7
Dependency can be
- Horizontal
- Vertical
- None of the above
- Both A & B
Answer Key: D
Question No. 8
Question No. 9
A priority plan for the components needed to make the products in the Master production schedule (MPS) called
- Production Activity control (PAC)
- Material Requirements planning (MRP)
- Capacity Requirement planning
- All of the above
Answer Key: B
Question No. 10
The plan must be checked against available capacity when needed to make the components is called the process of
- Capacity Requirement planning
- Material Requirements planning (MRP)
- Production Activity control (PAC)
- A & C
Answer Key: A
Question No. 11
The computer software program that organizes and maintains the bills of material structures and their linkage is called:
- Inventory record
- Purchasing record
- Bills of material processor
- Procurement of material and supplies
Answer Key: C
Question No. 12
Master production schedule, inventory records and bills of material are three major inputs to
- Material Requirements planning (MRP) System
- Production activity Control
- Manufacturing Planning and Control (MPC) Function
- Capacity Requirements planning (CRP)
Answer Key: A
Question No. 13
Question No. 14
Question No. 15
Question No. 16
When a calculation is made to find out how many are needed, the quantities available must be considered in:
- Maintaining the bills of material structures
- Linkage between manufacturing planning and control system
- Inventory records
- Both A & C
Answer Key: C
Question No. 17
Question No. 18
Question No. 19
Question No. 20
Question No. 21
Question No. 22
A bill is used when companies usually make more than one product and the same components are often used in several products
- Single-level bill
- Multiple bill
- Multilevel bill
- Indented bill
Answer Key: B
Question No. 23
Question No. 24
By using following product tree, how many Ks are needed to make 200Xs and 150 Ys?
Figure from example problem page no 85
- 1900 Ks
- 900 Ks
- 2100 Ks
- 800 Ks
Answer Key: A
Question No. 25
Question No. 26
Summarized parts list:
- The lists of all the parts needed to make one complete assembly
- Does not contain any information about the way the product is made or assembled
- It’s the list of comments are linked to their parents by listing them immediately below the parents
- Both A & B
Answer Key: D
Question No. 27
Question No. 28
Question No. 29
Question No. 30
Question No. 31
Question No. 32
A pegging report:
- Similar to a where-used report
- Shows only those parents for which there is an existing requirement
- Shows the parents creating the demand for the components, the quantities needed , and when they are needed
- All of the above
Answer Key: D
Question No. 33
Product design engineers sometimes change the design of a product and the components used. These changes must be recorded and controlled. The bill provides the method for doing so is called
- Engineering change control
- Production change control
- Demand change control
- Both A & B
Answer Key: A
Question No. 34
Question No. 35
Question No. 36
Which of the following are the purposes of material requirement planning so items in the master production schedule are made on time?
- To determine the components needed
- To determine the quantities
- To determine the due dates
- All of the above
Answer Key: D
Question No. 37
Question No. 38
The process of placing the exploded requirements in their proper periods based on lead time is called
- Offsetting
- Exploding the equipments
- Production plan
- Where-used reports
Answer Key: A
Question No. 39
If there are 20 as in stock, only 30 needs to be made, then the requirements for components parts would be:
Reduced accordingly
Increased accordingly
Added accordingly
Both B & C
Answer Key: A
Question No. 40
Which of the following is the right calculation for obtaining the net requirements?
Gross Requirement - Available inventory
Gross Requirement x Available inventory
Gross Requirement / Available inventory
None of the above is true
Answer Key: A
Question No. 41
Question No. 42
Question No. 43
Question No. 44
Planning horizon means
- The number of periods in the record
- The most current period in the record
- The quantity of the records
- None of the above
Answer Key: A
Question No. 45
At the MRP planning level, the process of priority plans must be checked against available capacity is called
- Master Production schedule (MPS)
- Capacity Requirements planning (CRP)
- Production activity control (PAC)
- Manufacturing Planning and control function (MPC)
Answer Key: B
Question No. 46
Question No. 47
Question No. 48
Question No. 49
Question No. 50
Question No. 51
Question No. 52
The message in which the planner must tell the MRP software of all actions taken that will influence the MRP records called
- Exception messages
- Transaction messages
- Bottom-up replanning
- None of the above
Answer Key: B
Question No. 53
Which of the following are three important factors must consider in managing the material requirements plan?
- Priority, Bottom-up Replanning and reducing system nervousness
- Planned orders, released orders and firm planned orders
- Priority, Exception message and transaction message
- None of the above is true
Answer Key: A
Question No. 54
|